SUMMER 2025 CONSTRUCTION 

June Update - Thank you for your cooperation and patience while our School Sites are under construction. We are excited for these upcoming improvements to our Schools!

  • BIS: The Administration Office Alterations construction will start soon and continue into the new school year. The BCE Donor Plaza and the Landscaping and Irrigation projects will begin this Summer. Additionally, Drainage Improvements to the hill between the basketball courts and Wing 7/8 are scheduled be completed.
  • Franklin: The Administration Office Renovation and temporary Admin construction will begin at the end of the 24/25 school year. Alterations to the Kindergarten / TK Play Structure will be completed this Summer.
  • Hoover: Both the Exterior Painting project and the Drainage Improvements to the hillside above the picnic tables are expected to be completed this Summer.
  • Lincoln: HVAC Upgrades and Rooftop Solar installations are scheduled to be completed this Summer. Prep for the new Shade Structure will begin.
  • McKinley: The new TK Building construction will continue into the coming school year. The Turf Field & North Play Yard construction will start this Summer and is expected to be completed in Early Fall. Exterior Painting work will be completed this Summer. 
  • Roosevelt: No construction currently planned for this Summer.
  • Washington: The Kindergarten Play Structure will receive TK modifications. 
  • District Office: Modernization construction is underway. During construction, the District Office has relocated to 2385 Trousdale Drive, just below the Franklin parking lot.

BSD STRATEGIC PLAN - MAY 2025

 
The most recent BSD Master Plan for the future planning of our facilities was completed in 2016. As part of our long-term forecasting, and as a stipulation for participation in the new Prop. 2 State School Facilities Program (state grants), the District needs to have a Master Plan that has been updated within the past 5 years.
 
The District is beginning this planning, included required document gathering, and will be engaging the Burlingame Community this Fall with a series of community meetings and opportunities to comment. These will include:
  • Site Meetings at each School: everyone will be welcome at these evening meetings
  • Student Meetings: Leadership groups
  • Interviews with District Departmental Leaders: Special Education, Education Services, Health Services, Human Resources, Technology Services, etc.
  • Online Community Survey
  • Board of Trustee Work Sessions
The Question we, the Community, are asking ourselves is... How should our School Facilities be improved, altered or replaced in order to best serve the long-term needs of the District and its students?
 

FACILITIES PROJECTS - MARCH 2025 UPDATE

 
Current Measure O Projects
  • HVAC Replacements & New Air Conditioning at Franklin, Hoover, McKinley (MPR) and Washington
  • Rooftop Solar, HVAC Replacement & New Air Conditioning at Lincoln
  • McKinley New TK Building
  • District Office Modernization
  • BIS Admin Building Exterior Shell Repair
  • Franklin Main Office Entry Alterations
  • McKinley New Turf Field & Garden
  • BCE Donor Plaza at BIS
  • BIS Hillside Drainage Improvements
  • Hoover Hillside Drainage Improvements
  • BIS Landscaping & Irrigation Phase 1
  • New BSD Maintenance Garage
  • New Furniture for Offices (Principals, Vice Principals, Resource / Specialist)
  • BIS Building 1 Modernization (Re-Design)
  • BIS Fire Alarm Replacement (Design)
  • Franklin Fire Alarm Replacement (Design)
  • BSD Master Plan 2025

 Future Measure O Projects (Tentative)

  • Lincoln New Admin / Library / Classroom Building
  • McKinley Mechanical Unit Replacement
  • Washington New Library Building, Turf Field and Play Structure
  • Landscape and Irrigation Replacement – All School Sites
  • Franklin TK Play Structure
  • Lincoln TK Play Structure
Completed Measure O Projects
  • Lincoln Hardcourt Improvements
  • District-wide Landscape & Irrigation Assessment / Master Plan
  • BIS Old Gym Demolition
  • District-wide New Classroom Furniture
  • Hoover Hillside Tree Removal & Pruning
  • Transitional Kindergarten Preparations (2022) (CEQA)
  • McKinley Irrigation and Barrier at El Camino Real
  • Workforce Housing Study
  • Lincoln New Play Structure and Playground Alterations
  • Hoover Hillside Drainage Mitigation (new drainage structure and concrete swale)
  • BIS New Student Recreation Center (SRC)
  • BIS Auditorium Modernization
  • Roosevelt MPR Stucco Wall Replacement
  • New Backpack Hooks at Franklin, McKinley and Washington
  • Roosevelt HVAC Replacement & New Air Conditioning
  • CA Distinguished School & National Blue Ribbon Signage at BIS, Franklin, Hoover, Lincoln and Washington
  • McKinley Interior Alterations
  • Solar Canopy Installations at BIS, McKinley, Roosevelt and Washington
  • Temporary District Office at Franklin
  • McKinley Play Yard Re-Striping (post-solar canopy installation repairs)
  • Roosevelt Play Yard Re-Striping (post-solar canopy installation repairs)
  • District-wide New Electronic Scrolling Marquee Signs
  • District-wide New Staff Lounge Furniture
  • BIS HVAC Replacement & New Air Conditioning

Facilities Projects with Non-Measure O Funds

  • District-wide Re-Keying (Deferred Maintenance)
  • MPR Dishwasher Replacements at Lincoln, McKinley, Roosevelt and Washington (General Fund & Cafeteria Fund)
  • BIS Sewer Line Replacement (Deferred Maintenance)
  • District-wide Irrigation Central Controls Replacement (Deferred Maintenance)
  • TK Classroom Furniture (Developer Fees) – In Progress
  • Franklin Bookcase Replacements (Developer Fees) – In Progress
  • BIS Building 11 HVAC & Controls Replacement (Deferred Maintenance) – In Progress
  • MPR Water Heater Replacements (Deferred Maintenance) – In Progress
  • Roosevelt Retaining Wall Repair (Developer Fees) -– In Progress
  • Hoover Exterior Painting (Deferred Maintenance) – In Progress
  • McKinley Exterior Painting (Deferred Maintenance) – In Progress
  • Fire Alarm Repairs at Roosevelt and Washington (Deferred Maintenance) – In Progress

MEASURE M & O PROJECT UPDATES - SEPTEMBER 2024

CONSTRUCTION CONTINUES DURING 2024/2025 SCHOOL YEAR

July 2024 Update - We would like to thank our educational community for their assistance and cooperation during our construction to create permanent improvements to our educational spaces. 

  • BIS: Major HVAC Upgrades occurring on campus. Solar Canopy installation is complete and awaiting PG&E interconnection. Design Tasks: BIS Building 1 New Central Kitchen, BIS Admin Exterior Shell Repair.
  • Franklin: The Temporary District Office construction continues. Play structure will be getting new rubberized surfacing. HVAC Upgrades are underway. Design Tasks: Admin Office Alterations.
  • Hoover: HVAC Upgrades are underway.
  • Lincoln: HVAC Upgrades and Rooftop Solar installations are scheduled to start this month.
  • McKinley: North playground re-striping and new basketball courts will be installed this summer. Portables have been demolished in preparation for new Solar Canopy. New HVAC for the MPR is underway.
  • Roosevelt: HVAC Upgrades are underway. New Solar Canopy is complete and awaiting PG&E interconnection. Playground re-striping will occur in August.
  • Washington: HVAC Upgrades are underway. Play structure will be getting new rubberized surfacing. Dirt area adjacent to Portables will also get new rubberized surfacing.
  • District Office: Modernization construction will begin in August.
 

DISTRICT PREPARES FOR SUMMER 2024 CONSTRUCTION

At its June 18, 2024 Regular Board Meeting, the Board approved:

 

  • Play Equipment at Franklin and Washington to OMNIA for the Franklin play structure surfacing upgrade and replacement for two hundred nine thousand three hundred thirty-nine dollars ($209,339), Washington play structure surfacing upgrade and replacement one hundred thirty-seven thousand seven hundred thirteen dollars and eighty-three cents ($137,713.83) and Washington new rubberized surfacing at direct area for thirty-eight thousand two hundred seventy-two dollars ($38,272).
 

BOARD PASSES RESOLUTION SUPPORTING AWARD OF CalSHAPE GRANT

At its June 11, 2024 Regular Meeting, the Board passed a resolution with the California Energy Commission for a plumbing grant from the Commission’s CalSHAPE grant program. The CalSHAPE plumbing program is intended to allow Districts to replace older, inefficient fixtures with new more efficient fixtures. This should therefore help reduce water usage by the District, which is paid from the General Fund.

 

At its June 11, 2024 Regular Board Meeting, the Board approved construction on:

  • District Office Access, Bid and HVAC Bid Results to Rodan Builders submitted a bid in the amount of three million four hundred forty-four thousand five hundred ninety-five dollars ($3,444,595). 
  • McKinley TK Classroom CEQA Notice of Exemption prepared by David J. Powers and submitted to the State Clearinghouse and County Recorder Office.
 

BOARD PASSES RESOLUTIONS SUPPORTING ENERGY MODERNIZATION AND SUSTAINABILITY PROGRAM

At its May 14, 2024 Regular Meeting, the Board passed the following resolutions:

  • Amendment #1 for Energy Conservation Services with Climatec LLC for the District Office in the amount of one hundred seventy-seven thousand four hundred sixty dollars ($177,460). 
  • Adoption of a Fee Justification Study and the Increase in School Developer Fees to Residential rate per square foot: Old:  $4.79; New:  $5.17. Commercial rate per square foot: Old:  $0.78; New:  $0.84.

 

At its May 14, 2024 Regular Board Meeting, the Board approved construction on:

 

  • BCE Donor Plaza at BIS to Landscape Architects Callander Associates (CALA) for seventy thousand dollars ($70,000). 
  • Deferred Maintenance Five Year Plan 2023/24 through 2027/28 was approved in the following construction categories: plumbing, HVAC, electrical, roofing, painting, flooring, asbestos abatement, lead/HVAC removal and rekeying in the amount of four million nine hundred sixty-four thousand thirty-four dollars ($4,964,034). 
  • BIS Building 1 Modernization Schematic Updated Design to Hamilton + Aitken Architects (HAA) for one million one hundred sixty-seven thousand eight hundred thirty-eight dollars ($1,167,838).
  • Measure O Budget Allocation Increase to one hundred fifteen million two hundred forty-eight thousand eight hundred forty-six dollars ($115,248,846).  
  • Additional Services for Program Management to Dreiling Terrones Architecture (DTA) for one million forty-two thousand three hundred fifty dollars ($1,042,350).